Our first milestone was ceiling works by 28th
August
- · Dismantling of existing partition, false ceiling, flooring and cleaning of debris from site
- · G I frames for drywall partitions with glass wool for sound insulation of partition.
- · Laying of raceways for power and data
- · Sprinkler , bending and moving of pipes is been carried out as per the layout.
- · False ceiling frames
- · Ac ducting installed with insulation
- · Plumbing for cafeteria sink has been done.
- · Washroom works going on Civil